1.    Motiriri Enterprises provides the following data relating to component B97020314.
Cost of raw material                                       N10 per unit
Usage per day                                                 100 units
Minimum re-order period                                20 days
Maximum re-order period                               30 days
Cost of ordering materials                              N400 per order
Carrying cost                                                   10% per annual
Assume that each year consists of 48 working weeks of 5 days per week.
Required: Calculate:
(i) The Re-Order Level       (ii)  The Re-Order Quantity   (iii)  The Maximum Level
(iv)  The Minimum Level     (v) The Average Level
(b)  Write short note on the following terms:
i. Cost        ii. Cost Unit      iii. Cost Centre
(c) List three element of cost known to you.